Framing to final, every phase scheduled with the sub it needs, across all the active builds, so the trades line up in order and nothing sits.

On site this week

The Wolffork Valley house
Tile & flooring
Stekoa Tile & Stone
On site now
The Screamer Mountain house
Mechanical rough-ins
Currahee Electric
On site now
The Betty's Creek cabin
Framing
Persimmon Framing
Waiting on the sub
The Wolffork Valley house

Wolffork Valley, Rabun Gap

7 of 9 phases done
Site & grading
Tallulah Grading & Excavation · Jan 31 to Feb 8
Done
Foundation
Betty's Creek Concrete · Feb 10 to Mar 4
Done
Framing
Persimmon Framing · Mar 6 to Apr 9
Done
Roof & dry-in
Screamer Mountain Roofing · Apr 11 to Apr 29
Done
Mechanical rough-ins
Currahee Electric · May 1 to May 29
Done
Insulation & drywall
Chechero Drywall & Paint · May 31 to Jun 30
Done
Trim & cabinets
Kelsey Cabinetry · Jul 20 to Sep 10
Done
Tile & flooring
Stekoa Tile & Stone · Sep 8 to Sep 25
On site now
Fixtures & final
Handled in-house · Sep 29 to Oct 18
Scheduled
The Screamer Mountain house

Screamer Mountain, Clayton

4 of 9 phases done
Site & grading
Tallulah Grading & Excavation · Apr 19 to Apr 27
Done
Foundation
Betty's Creek Concrete · Apr 29 to May 23
Done
Framing
Persimmon Framing · May 25 to Jun 28
Done
Roof & dry-in
Screamer Mountain Roofing · Jun 30 to Jul 20
Done
Mechanical rough-ins
Currahee Electric · Aug 25 to Sep 28
On site now
Insulation & drywall
Chechero Drywall & Paint · Oct 2 to Oct 22
Scheduled
Trim & cabinets
Kelsey Cabinetry · Oct 26 to Nov 19
Coming up
Tile & flooring
Stekoa Tile & Stone · Nov 23 to Dec 15
Coming up
Fixtures & final
Handled in-house · Dec 19 to Jan 14
Coming up
The Betty's Creek cabin

Betty's Creek, Dillard

2 of 9 phases done
Site & grading
Tallulah Grading & Excavation · Jul 23 to Jul 30
Done
Foundation
Betty's Creek Concrete · Aug 1 to Aug 17
Done
Framing
Persimmon Framing · Sep 6 to Oct 4
Waiting on the sub

Persimmon got held up finishing the Nacoochee job. They start here Monday, weather holding.

Roof & dry-in
Screamer Mountain Roofing · Oct 8 to Oct 20
Scheduled
Mechanical rough-ins
Currahee Electric · Oct 24 to Nov 15
Coming up
Insulation & drywall
Chechero Drywall & Paint · Nov 19 to Dec 7
Coming up
Trim & cabinets
Kelsey Cabinetry · Dec 11 to Jan 4
Coming up
Tile & flooring
Stekoa Tile & Stone · Jan 8 to Jan 28
Coming up
Fixtures & final
Handled in-house · Feb 1 to Feb 28
Coming up