Each build's draw schedule against phase completion, so the milestone money gets billed and cleared instead of slipping.

The drywall and trim complete draw is ready to bill and past its date. That is real money sitting on the table. Record it invoiced below to move it along.

The Screamer Mountain house

The Hartwells · Screamer Mountain, Clayton

$1,340,000
contract price
Cleared
$335,000
Invoiced, awaiting
$268,000
Left to bill
$737,000
Deposit at signing
Cleared Apr 20
$134,000
Cleared
Foundation complete
Cleared May 27
$201,000
Cleared
Framing and dry-in complete
Invoiced Jul 23
$268,000
Invoiced
Rough-ins complete
Scheduled for Sep 30
$201,000
Coming up
Drywall and trim complete
Scheduled for Nov 21
$268,000
Coming up
Final and completion
Scheduled for Jan 16
$268,000
Coming up
The Wolffork Valley house

The Bramletts · Wolffork Valley, Rabun Gap

$985,000
contract price
Cleared
$591,000
Invoiced, awaiting
$0
Left to bill
$394,000
Deposit at signing
Cleared Feb 1
$98,500
Cleared
Foundation complete
Cleared Mar 6
$147,750
Cleared
Framing and dry-in complete
Cleared Apr 13
$197,000
Cleared
Rough-ins complete
Cleared May 31
$147,750
Cleared
Drywall and trim complete
Ready Mon, Sep 14
$197,000
Past its date
Final and completion
Scheduled for Oct 16
$197,000
Coming up
The Betty's Creek cabin

The Okonkwos · Betty's Creek, Dillard

$720,000
contract price
Cleared
$72,000
Invoiced, awaiting
$0
Left to bill
$648,000
Deposit at signing
Cleared Jul 25
$72,000
Cleared
Foundation complete
Ready Sat, Sep 19
$108,000
Ready to bill
Framing and dry-in complete
Scheduled for Oct 26
$144,000
Coming up
Rough-ins complete
Scheduled for Nov 25
$108,000
Coming up
Drywall and trim complete
Scheduled for Dec 25
$144,000
Coming up
Final and completion
Scheduled for Feb 13
$144,000
Coming up