Hollis Creek
Builders

You are seeing The Hartwells' private page, exactly as they see it.

Back to owner view
Your home

The Screamer Mountain house

A four-bedroom on the south face of Screamer Mountain, framed and under roof, now getting its rough-ins.

A few choices are waiting on you

Master bath
Floor tile
Waiting on you

Honed slate, 12 by 24

The honed slate reads warm underfoot and holds up in a wet room. It sits well with the shower niche you already picked.

Needs an answer by Jul 19
Kitchen
Countertop
Waiting on you

Honed granite, Pearl Grey

A honed granite hides water spots better than a polished top and works with the walnut cabinets.

Needs an answer by Jul 25
Already decided
Entry
Front door
Approved

Knotty alder, clear finish

A solid alder door with a clear finish, so the grain shows.

Approved June 24, 2026 at 8:30 PM

Yes, the alder. It looks like the mountain.

Exterior
Board and batten stain
Approved

Cedar, semi-transparent

A semi-transparent cedar tone that lets the wood grain read.

Approved June 16, 2026 at 8:30 PM

Love it. That is the one.

How your home is coming along

Electrical rough-in
July 14, 2026 · 2 days ago

Currahee is pulling wire this week. Once they finish we set the inspection, then insulation can go in.

Plumbing topped out
July 11, 2026 · 5 days ago

Plumbing passed its inspection today. Electrical is next.

Rough-ins started
June 26, 2026 · 20 days ago

Plumbing and HVAC crews are in. You will see a lot of pipe and duct before it starts looking like walls again. That is normal.

Under roof
May 21, 2026 · 56 days ago

The roof is on and the house is dried in. From here the weather stops mattering as much and we move inside.

Where things stand

  1. Site & gradingDone
  2. FoundationDone
  3. FramingDone
  4. Roof & dry-inDone
  5. Mechanical rough-insHappening now
  6. Insulation & drywallUp next
  7. Trim & cabinetsComing up
  8. Tile & flooringComing up
  9. Fixtures & finalComing up

Payments

Paid to date $335,000 of $1,340,000.

  • Deposit at signingPaid$134,000
  • Foundation completePaid$201,000
  • Framing and dry-in completeBilled, in process$268,000
  • Rough-ins completeComing up$201,000
  • Drywall and trim completeComing up$268,000
  • Final and completionComing up$268,000